The timetable of the project

 

Begin of phase End of phase Phase name
01.07.2024 30.06.2028 Data acquisition
01.07.2024 30.06.2028 Coordination and dissemination
01.10.2024 30.09.2028 Detection of runoff changes
01.01.2025 31.12.2027 Rainfall-runoff modelling
01.01.2025 31.12.2027 Hybrid simulation framework
01.01.2025 31.03.2028 Case studies